LTS Global Solutions’ New Facility in Hams Hall, Birmingham

LTS Global Solutions will soon be moving to a brand new eco built facility in Hams Hall in Birmingham.

Centrally located 10 miles from Birmingham city centre and just one mile from M42 junction 9, the new state-of-the-art facility built by Prologis offers unrivalled opportunities for LTS and its customers.

Being at the heart of the UK’s national motorway network and with an on-site intermodal rail freight terminal linking to three seaports and the Channel Tunnel, means LTS Hams Hall is perfectly connected to serve UK and International customers. 

The 131,780 sq. ft. site consists of 119,255 sq. ft. of warehouse space and 12,525 sq. ft. of office space covering two floors. The 15-metre high warehouse will have two 2-level access doors, 12 dock access doors and in excess of 50 HGV parking spaces. Staff and visitors will benefit from a modern operational facility featuring a canteen, gym, showers and changing facilities, as well as a grass and picnic area, cycle shelter and 90 car parking spaces with electric car charging points.

Completion is expected in mid-July when we will commence fit out with a target date of being operational by the end of quarter 3.

3rd August 2022
A pallet being stored
3rd August 2022

Our first put away

Today we hit the biggest milestone, our first pallet was put away using one of our new VNA trucks. This is the culmination of a lot of hard work by a brilliant team coming together. There will be some long days ahead and lots still to do but for now, we reflect on what it has taken to get us this far.

We have a great building and equipment, plenty of space and a commitment to get it right and strive for better.  If you’d like to join us either as an employee or customer, then now is the time. Get in touch!

1st August 2022
A key box containing a variety of keys
1st August 2022

We've got the keys

1st of August will be a day etched in our memories, we completed on the lease of our new facility and got the keys! Huge thank you to Prologis and Winvic for the handover and Gerald Eve for doing the snagging list. There are some bits to finish but we can now get on with the internal works and fitting out the offices. There are some updated images in the gallery if you want to check them out. 

26th July 2022
A modular building inside the LTS Global Solutions warehouse
26th July 2022

The Logistics Office is in Position

We have taken delivery of a modular building for our Logistics team – nicely colour coordinated, and with it being positioned in the warehouse they won’t have as far to walk.  It looks tiny in comparison to the warehouse but we can assure you there is plenty of room in it.

22nd July 2022
22nd July 2022

We welcomed the UKWA

We were delighted to welcome the United Kingdom Warehouse Association to view the progress of the facility. The build is coming on nicely and the racking is going up fast. We’re into the final month before we move now, so we have plenty of moving parts and schedules to maintain.

1st July 2022
Some of the LTS team checking out the warehouse
1st July 2022

Staff Visit Site

It was an exciting day as we took some of our team to visit the site. The interior is really starting to take shape now so they were able to see where they’d be working and the facilities they’d have. The team were impressed with the building and excited about moving in at the end of August.  To view more internal images please check out the gallery.

17th June 2022
Driver Tom with LTS vehicle in yard
17th June 2022

First Trucks on Site!

The building is really coming on.
Our first two LTS vehicles visited what will become their new home to drop off the initial loads of racking.
The racking is being assembled next week ready for installation. You can view more images in the gallery.

27th May 2022
Aerial view of LTS Hams Hall, May 2022
27th May 2022

Progress

There is so much to think about moving into a brand new building. This week the fire safety installation has begun and we have appointed the suppliers for lighting, CCTV, office partitions and the modular building.

18th May 2022
LTS Hams Hall Warehouse, May 2022
18th May 2022

Taking Shape

The site is really starting to take shape and in less than a month we can begin to install the warehouse racking!

19th April 2022
LTS Hams Hall, Birmingham
19th April 2022

It's official

LTS Global Solutions agree a 10-year lease with Prologis for a new 131,780 sq ft unit at Prologis Park Hams Hall. Birmingham.

March 2022
Aerial image - March 2022
March 2022

A different perspective

We took some spectacular drone footage that visually shows the scale of the new premises.

9th February 2022
February 2022
9th February 2022

First site visit

Dave, Mirza and Gren got their feet dirty for the first time on site and explored what was to become the new LTS premises. 

January 2022
January 2022

To Infinity...

The focus group working on the project named it project Infinity, and yes we do have Toy Story characters too.

Dave – Buzz Light Year
Mirza – Mr Potato Head
Gren – Rex
Rachael – Hamm
James – Woody
Nigel – Sarge
Rachel – Jessie

October 2021
October 2021

First visit to Hams Hall

The site at Hams Hall in Birmingham became a location of interest and we commenced negotiations with Prologis. 

July 2021
July 2021

The journey begins...

After many years at our Tilton Road headquarters and long periods of sustained growth, it became apparent we required larger premises to continuing to deliver on the needs of our customers and partners. 

Get in touch

If you're interested in speaking with us about our new facility at Hams Hall in Birmingham, please fill in your details below and someone will get back to you. 

Alternatively, you can call us 0121 753 0080 or email on info@ltsglobalsolutions.com